Why is historical information useful in developing the project plan?
Constraints
Project Planning Methodology?
Project Plan
Work Authorization System?
Work Results?
How is the project plan used to in integrated change control?
Taking results of other planning processes and putting them into a coherent, consistent document.
The processes required to ensure that various elements of the project are properly coordinated.
Because it helps verify assumptions and assess identified alternatives.
Coordinating changes across the entire project.
Any structured approach to guide the project team in the development of a project plan.
Factors that limit the project management team's options.
A formal procedure to
A formal, approved document used to manage and control project execution.
sanction project work so that it is done at the proper time and in the proper sequence.
The project plan provides the baseline against which all changes are controlled.
Outcomes of activities performed to accomplish the project.
What is required in the decision making process?
Llife-Cycle Costing
Line Manager
Matrix Organization?
Network Logic?
Organization Planning
Parametric Estimating
Pareto Diagram
Work Package
Work Breakdown Structure
The concept of including acquisition, operating, and disposal costs when evaluating various alternatives.
Analyzing the problem to identify viable solutions and then making a choice from among them.
Any organization structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of individuals assigned to the project.
The manager of any group that actually makes a product or performs a service. Also called a functional manager.
Identifying, documenting, and assigning project roles, responsibilities, and reporting relationships.
Any continuous series of connected activities in a project network diagram.
A histogram, ordered by frequency of occurrence, that shows how many results were generate by each identified cause.
An estimating technique that uses a statistical relationship between historical data and other variables to calculate an estimate.
A task oriented structure that organizes and defines total work to be accomplished in a
A deliverable at the lowest level of the Work
project. Each level represents an increasingly detailed definition of a project component.
Breakdown Structure. A work package may be divided into activities.
Float / Slack
Critical Path Method(CPM)
Backward Pass
Corrective Action
Budgeted Cost of Work Scheduled (BCWS)
Baseline
Arrow Diagramming Method (ADM)
Administrative Closure
Backward Pass
Ac t iv i t y
A network analysis technique used to predict project duration by analyzing which sequence of tasks has the least amount of scheduling flexibility (i.e. the least amount of float).
The amount of time that an activity may be delayed from its early start date without delaying the project finish date. Float is a arithmetic calculation and can change as the project progresses and changes are made to the project plan. Also called slack.
Changes made to bring expected future performance performanc e of the project into line with the project plan.
The calculation of late finish dates and late start dates for the uncompleted portions of all network activities. Determined by working backwards through the network logic from the project's end date.
"The original planor(for project, a work package, an aactivity), plus or minus approved changes. Usually used with a modifier (e.g., cost baseline, schedule baseline, performance measurement baseline)."
Theestimates sum of the approved cost (including any overhead allocation) for activities (or portions of activities) scheduled to be performed during a given period (usually project-to-date). A network diagramming technique in which activities are represented by
"Generating, gathering, and disseminating information to formalize project completion."
arrows. The ofand the the arrow represents the tail start head represents the finish of the activity. Activities are connected at points called nodes to illustrate the sequence in which the activities are expected to be performed.
"An element of work performed during the course of a project. An activity normally has an
The calculation of late finish dates and late start dates for the uncompleted portions of all network activities. Determined by working backwards through the network logic from the project’s end date. The end date may be calculated in a forward pass or set by the customer or sponsor.
expected duration, an expected cost, and expected resource requirements. Activities are often subdivided into tasks."
Activity Definition
Activity Description
Activity Duration Estimating
Cost of Work Performed (ACWP)
A c t u a l F i n i s h D at e
Actual Start Date
Administractive Closure
Application Area
Bar Chart
Baseline
A short phrase or label used in a project network diagram. The activity description normally describes the scope of work of the activity.
Identifying the specific activities that must be performed in order to produce the various project deliverables.
Total costs incurred in accomplishing work during a given time period.
Estimating the number of work periods which will be needed to complete individual activities.
The point in time that work actually started on an activity.
The point in time that work actually ended on an activity.
A category of projects that have common elements not present in all projects. Application areas are usually defined in terms of either the product of the project. Application areas often overlap. "The original plan (for a project, a work package, or an activity), plus or minus approved changes. Usually used with a modifier (e.g., cost baseline, schedule baseline, performance measurement baseline)."
"Generating, gathering, and disseminating information to formalize project completion."
"A graphic display of schedule-related information. In the typical bar chart, activities or other project elements are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars. Also called a Gantt chart."
Work Package
Word Breakdown Structure
Workaround
Total Quality Management (TQM)
Target Start Date (TS)
Target Finish Date (TF)
Time-Scaled Network Diagram
Team Development
Target Completion Date (TC)
Successor Activity
A deliverable-oriented grouping of project elements which organizes and defines the total scope of the project.
A deliverable at the lowest level of the work breakdown structure. A work package may be divided into activities.
A common approach to implementing a quality improvement program within an organization.
A response to a negative risk event. Distinguished from contingency plan in that a workaround is not planned in advance of the occurrence of the risk event.
The date work is planned (targeted) to finish on an activity.
The date work is planned (targeted) to start on an activity.
Developing individual and group skills to enhance project performance.
Any project network diagram drawn in such a way that the positioning and length of the activity represents its duration. Essentially, it is a bar chart that includes network logic.
(1) In the arrow diagramming method, the activity which departs a node. (2) In the precedence diagramming method, the “to” activity.
An imposed date which constrains or otherwise modifies the network analysis.
Subnet
Start Date
Statement of Work (SOW)
Stakeholder
St af f A cq u i si t i o n
Source Selection
Solicitation Planning
What is Project Risk Management?
How is Monte Carlo analysis used in schedule simulations?
What is the difference between a risk and a problem?
A narrative description of products or services to be supplied under contract.
A subdivision of a project network diagram usually representing some form of subproject.
Individuals and organizations who are involved in or may be affected by project activities.
A point in time associated with an activity’s start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.
Choosing from among potential contractors.
Getting theneeded human resources assigned to and working on the project.
The process concerned with identifying, analyzing, and
Documenting
responding to project risk. It also includes maximizing the results of positive events as well as minimizing the consequences of adverse events to project objectives.
product requirements and identifying potential sources.
A risk is a future event; it has not yet
To perform the project many times in order to
occurred. A problem, on the other hand, currently exists.
provide a statistical distribution of the calculated results.
Solicitation
Should-Cost Estimates
Scope Verification
Scope Planning
Scope Definition
Scope Change Control
Scope Change
Scope
Scheduled Start Date (SS)
Scheduled Finish Date (SF)
An estimate of the cost of a product or service used to provide an assessment of the reasonableness of a prospective contractor’s proposed cost.
Obtaining quotations, bids, offers, or proposals as appropriate.
Developing a written scope statement that includes the project justification justifi cation,, the major deliverables, and the project objectives.
Ensuring that all identified project deliverables have been completed satisfactorily.
Controlling changes to project scope.
Decomposing the major deliverables into smaller, more manageable components to provide better control.
The sum of the
Any change to the
products and services to be provided as a project.
project scope changescope. almostAalways requires an adjustment to the project cost or schedule.
The point in time work was scheduled to finish on an activity. The scheduled finish
The point in time work was scheduled to start on an activity. The scheduled start
date is normally within the range of dates delimited by the early finish date and the late finish date.
date is normally within the range of dates delimited by the early start date and the late start date.
Schedule Variance (SV)
Schedule Performance Index (SPI)
Schedule Development
Schedule Control
S-Curve
Risk Response Development
Risk Response Control
What type of change constitutes one of the major areas of cost growth?
What are the What is privity of contract?
characteristics of a well-written SOW?
The ratio of work performed to work scheduled (BCWP/BCWS).
(1) Any difference between the scheduled completion of an activity and the actual completion of that activity. (2) In earned value, BCWP less BCWS.
Controlling changes to the project schedule.
Analyzing activity sequences, activity durations, and resource requirements to create the project schedule.
Defining enhancement steps for opportunities and mitigation steps for threats.
Graphic display of cumulative costs, labor hours, or other quantities, plotted against time. The name derives from the S-like shape of the curve (flatter at the beginning and end, steeper in the middle) produced on a project that starts slowly, accelerates, and then tails off.
Change to project scope.
Responding to changes in risk over the course of the project.
The SOW shoulbe be clear, complete, and concise and include a description of any collateral services required.
A doctrine of law that recognizes the contractual relationship existing between a buyer and its prime contractor.
Risk Quantification
Risk Identification
Risk Event
Retainage
Responsibility Assignmentt Matrix Assignmen (RAM)
Resource Planning
Resource-Limited Schedule
Resource Leveling
Reserve
Request (RFQ) for Quotation
Determining which risk events are likely to affect the project.
Evaluating the probability of risk event occurrence and effect.
A portion of a contract payment that is held until contract completion in order to ensure full performance of the contract terms.
A discrete occurrence that may affect the project for better or worse.
Determining what resources (people, equipment, materials) are needed in what quantities to perform project activities.
A structure which relates the project organization structure to the work breakdown structure to help ensure that each element of the project’s scope of work is assigned to a responsible individual.
Any form of network analysis in which scheduling decisions (start and finish dates) are driven by resource management concerns (e.g., limited resource availability or difficult-to-manage changes in resource levels).
A project schedule whose
Generally, this term is equivalent to request for proposal. However, in some application areas it may have a narrower or more specific meaning.
start expected and finishresource dates reflect availability. The final project schedule should always be resource-limited. A provision in the project plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated. The specific meaning of the modified term varies by application area.
Request for Proposal (RFP)
Remaining Duration (RDU)
Quality Planning
Quality Control (QC)
Quality Assurance (QA)
Projectized Organization
As a PMP, what laws,
Project Time Management
regulations, and ethical standards govern your professional practice?
What is meant
What are the two
when someone said to be is ethnocentric?
ways project resources are obtained?
The time needed to complete an activity.
A type of bid document used to solicit proposals from prospective sellers of products or services. In some application areas it may have a narrower or more specific meaning.
(1) The process of monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance. (2) The organizational unit that is assigned responsibility for quality control.
Identifying which quality standards are relevant to the project and determining how to satisfy them.
Any organizational structure in which the project manager has full authority to assign priorities and to direct the work of individuals assigned to the project.
(1) The process of evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards. (2) The organizational unit that is assigned responsibility for quality assurance.
Those of the state or
A subset of project management that
province and/or country where you provide project management services.
includes the processes required ensure timely completion of theto project. It consists of activity definition, activity sequencing, activity duration estimating, schedule development, and schedule control.
A belief in the Staffprocurement. acquisition and
inherent superiority of one's own culture.
What are the two ways project resources are obtained?
Project Team Members
Project Schedule
Project Risk Management
Project Quality Management
Project Procurement Management
Project Planning
Project Plan Execution
Project Plan Development
Project Plan
A subset of project management that includes the processes required to ensure that the project includes all of the work required, and only the work required, to complete the project successfully. It consists of initiation, scope planning, scope definition, scope verification, and scope change control.
Staff acquisition and procurement.
A subset of project management that includes the processes concerned with identifying, analyzing, and responding to project risk. It consists of risk identification, risk quantification, risk response development, and risk response control.
The planned dates for performing activities and the planned dates for meeting milestones.
A subset of project management that includes the processes required to acquire goods and services from outside the performing organization. It consists of procurement planning, solicitation planning, solicitation, source selection, contract administration, and contract close-out.
A subset of project management that includes the processes required to ensure that the project will satisfy the needs for which it was undertaken. It consists of quality planning, quality assurance, and quality control.
Carrying out the project plan by performing the activities included therein.
The development and maintenance of the project plan.
A formal, approved document used to guide both project execution and project control. The primary uses of the project plan are to document planning
Taking the results of other planning
assumptions and decisions, to facilitate communication among stakeholders, and to document approved scope, cost, and schedule baselines. A project plan may be summary or detailed.
processes and putting them into a consistent, coherent document.
Any schematic display of the logical relationships of project activities. Always drawn from left to right to reflect project chronology. Often incorrectly referred to as a “PERT chart.”
A collection of logically related project activities, usually culminating in the completion of a major deliverable.
The members of the project team who are directly involved in project management activities. On some smaller projects, the project management team may include virtually all of the project team members.
The individual responsible for managing a project.
An individual certified as such by the Project Management Institute.
A class of computer applications specifically designed to aid with planning and controlling project costs and schedules.
The application of knowledge, skills, tools, and techniques toproject activities activities in order to meet or exceed stakeholder needs and expectations from a project.
A subset of project management that includes the processesrequired to ensure that the various elements of the project are properly coordinated. coordinated. It consists of project plan development, project plan execution, and overall change control.
An inclusive term that describes the sum of knowledge within the profession of project management. As with other professions such as law, medicine, and accounting, the body of knowledge rests with the practitioners and academics who apply and advance it. The PMBOK includes proven, traditional practices which are widely applied as well as innovative and advanced ones which have seen more limited use.
A collection of generally sequential project phases whose name and number are determined by the control needs of the organization or organizations involved in the project.
Project Human Resource Management
Project Cost Management
Project Communications Management
Project Charter
Project
Program Evaluation and Review Technique (PERT)
Program
Procurement Planning
Predecessor Activity
Precedence Relationship
A subset of project management that includes the processes required to ensure that the project is completed within the approved budget. It consists of resource planning, cost estimating, cost budgeting, and cost control.
A subset of project management that includes the processes required to make the most effective use of the people involved with the project. It consists of organizational planning, staff acquisition, and team development.
A document issued by senior management that provides the project manager with the authority to apply organizational resources to project activities.
A subset of project management that includes the processes required to ensure proper collection and dissemination of project information. It consists of communications planning, information distribution, performance reporting, and administrative closure.
An event-oriented network analysis technique used to estimate project duration when there is a high degree of uncertainty with the individual activity duration estimates. PERT applies the critical path method to a weighted average duration estimate. Also given as Program Evaluation and Review Technique.
A temporary endeavor undertaken to create a unique product or service. A group of related
Determining what to procure and when.
projects managed in a coordinated way. Programs usually include an element of ongoing activity.
The term used in the precedence diagramming method for a logical relationship. In current
(1) In the arrow diagramming method, the
usage, however, relationship, logicalprecedence relationship, and dependency are widely used interchangeably interchangea bly regardless of the diagramming method in use.
activity enters a node. (2) Inwhich the precedence diagramming method, the “from” activity.
Precedence Diagramming Method (PDM)
PERT Chart
Performing Organization
Performance Reporting
Percent Complete (PC)
Path Convergence
Path
Pareto Diagram
Parametric Estimating
Overall Change Control
A specific type of project network diagram.
A network diagramming technique in which activities are represented by boxes (or nodes). Activities are linked by precedence relationships to show the sequence in which the activities are to be performed.
Collecting and disseminating information about project performance to help ensure project progress.
The enterprise whose employees are most directly involved in doing the work of the project.
In mathematical analysis, the tendency of parallel paths of approximate approximately ly equal duration to delay the completion of the milestone where they meet.
Anas estimate, expressed a percent, of the amount of work which has been completed on an activity or group of activities.
A histogram, ordered by frequency occurrence, thatof shows how many results were generated by each identified cause.
Coordinating changes across the entire project.
A set of sequentially connected activities in a project network diagram. An estimating technique that uses a statistical relationship between historical data and other variables (e.g., square footage in construction, lines of code in software development) to calculate an estimate.
Organizational Planning
Organizational Breakdown Structure (OBS)
Node
Network Path
Network Logic
Network Analysis
Near-Critical Activity
Monte Carlo Analysis
Monitoring
Modern Project Management (MPM)
A depiction of the project organization arranged so as to relate work packages to organizational units.
Identifying, documenting, and assigning project roles, responsibilities,and reporting relationships.
Any continuous series of connected activities in a project network diagram.
One of the defining points of a network; a junction point joined to some or all of the other dependency lines. See also arrow diagramming method and precedence diagramming method.
The process identifying earlyofand late start and finish dates for the uncompleted portions of project activities.
The collection of activity dependencies that make up a project network diagram.
A schedule risk assessment technique that performs a project simulation many times in order to calculate a distribution of likely results.
An activity that has low total float.
A term used to distinguish the current broad range of project
The capture, analysis, and
management (scope, time, quality, risk, etc.)cost, from narrower, traditional use that focused on cost and time.
reporting of project performance, usually as compared to plan.
Mi ti g a ti o n
M i l es t o n e Sch e d u l e
Milestone
Matrix Organization
Master Schedule
Management Reserve
Loop
S t a r t - t o - f i n i sh
St a r t - t o - st ar t
Fi n i s h - t o- f i ni s h
A summary-level schedule which identifies the major milestones. See also master schedule.
Taking steps to lessen risk by lowering the probability of a risk event’s occurrence or reducing its effect should it occur.
Any organizational structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of individuals assigned to the project.
A significant event in the project, usually completion of a major deliverable.
A separately planned quantity used to allow for future situations which are impossible to predict. Management reserves may involve cost or schedule. Management reserves are intended to reduce the risk of missing cost or schedule objectives. Use of management reserve requires a change to the project’s cost baseline.
A summary-level schedule which identifies the major activities and key milestones.
the “from” activity must start before the “to” activity can finish
A network path that passes the same node twice. Loops cannot be analyzed using traditional network analysis techniques such as CPM and PERT. Loops are allowed in GERT.
the “from” activity
the “from” activity
must finish before the “to” activity can finish
must before the “to”start activity can start
Finish-to-start
The four possible types of logical relationships
Logical Relationship
Line Manager
Why is the type of organizational structure important in project management?
When is the project team directory developed?
Which type of power should a project manager avoid?
Which type of power should a project manager use?
What are the five methods of dealing with conflict?
What is the highest level of need's in Maslow's hierarchy of needs?
the “from” activity must finish before the “to” activity can start
(1) The manager of any group that actually makes a product or performs a service. (2) A functional manager.
A dependency between two project activities, or between a project activity and a milestone.
As part of the staff acquisition phase of the project.
The structure of the organization organizatio n often constrains the availability under which resources become available to the project.
Should try to use reward and expert powers.
Avoid using coercive power.
Self-fulfillment through the development of
Smoothing, Withdrawl, Compromise, Forcing and Problem Solving
powers and skills, and a chance to use creativity.
Smoothing
What use does a Gantt Chart provide?
What is life-cycle costing?
What is a variable cost?
How is the cost performance index (CPI) figured?
Define what a payback period is?
What is internal rate of return (IRR)?
What is BCWS or PV? PV ?
How is schedule variance (SV) figured?
Whatcosts? are direct
To identify when a particular resource is (or will be) working on a particular task.
Deemphasizing the opponents' differences and emphasizing their commonalities over the issues in question.
Costs that rise directly with the size of the project.
The concept of including acquisition, operating, and disposal costs when evaluating various alternatives.
The number of times periods up to the point at which cumulative revenues exceed cumulative costs and, therefore, the project has turned a profit.
CPI = BCWP /ACWP or EV / AC
The percentage rate
Budgeted cost of work scheduled or planned value.
Costs incurred directly by a specific project.
that makes the present value of costs equal to the present value of benefits.
SV = or BCWP BCWS EV - -PV
Level of Effort (LOE)
Lead
Late Start Date (LS)
Late Finish Date (LF)
Lag
Invitation for Bid (IFB)
Initiation
Information Distribution
Hanger
Hammer
A modification of a logical relationship which allows an acceleration of the successor task. For example, in a finish-to-start dependency with a 10-day lead, the successor activity can start 10 days before the predecessor has finished.
Support-type activity (e.g., vendor or customer liaison) that does not readily lend itself to measurement of discrete accomplishment. It is generally characterized by a uniform rate of activity over a specific period of time.
In the critical path method, the latest possible point in time that an activity may be completed without delaying a specified milestone (usually the project finish date).
In the critical path method, the latest possible point in time that an activity may begin without delaying a specified milestone (usually the project finish date).
Generally, this term is equivalent to request for proposal. However, in some application areas it may have a narrower or more specific meaning.
A modification of adirects logicala relationship which delay in the successor task. For example, in a finish-to-start dependency with a 10-day lag, the successor activity cannot start until 10 days after the predecessor has finished.
Making needed information available to project stakeholders in a timely manner.
Committing the organization to begin a project phase.
An aggregate or summary activity (a group of related
An unintended break in a network path. Hangers
activities as one and reported is at shown a summary level). A hammock may or may not have an internal sequence.
are usually caused or by missing activities missing logical relationships.
Graphical Evaluation and Review Technique (GERT)
Grade
Functional Organization
Functional Manager
Fr ee Float ( FF)
Forward Pass
Float
Fixed Price Incentive Fee (FPIF) Contract
Firm Fixed Price (FFP) Contract
Finish Date
A category or rank used to distinguish items that have the same functional use (e.g., “hammer”) but do not share the same requirements for quality (e.g., different hammers may need to withstand different amounts of force).
A network analysis technique that allows for conditional and probabilistic treatment of logical relationships (i.e., some activities may not be performed).
A manager responsible for activities in a specialized department or function (e.g., engineering, manufacturing, marketing).
An organization structure in which staff are grouped hierarchically by specialty (e.g., production, marketing, engineering, and accounting at the top level; with engineering, further divided into mechanical, electrical, and others).
The calculation of the early start and early finish dates for the uncompleted portions of all network activities.
The amount of delayed time an activity can be without delaying the early start of any immediately following activities.
A type of contract where the
The amount of time that an activity may be delayed from its early start without delaying the project finish date. Float is a mathematical calculation and can change as the project progresses and changes are made to the project plan. Also called slack, total float, and path float.
buyer pays sellerby a the set amount (as the defined contract), and the seller can earn an additional amount if it meets defined performance criteria. A point in time associated with an activity’s completion. Usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, baseline, target or current.
A type of contract where the buyer pays the seller a setby amount (as defined the contract) regardless of the seller’s costs.
Fast Tracking
Expected Monetary Value
Exception Report
Event-on-Node
Estimate To Complete (ETC)
Estimate At Completion (EAC)
Estimate
Effort
Earned Value (EV)
Early Start (ES) Date
The product of an event’s probability of occurrence and the gain or loss that will result. For example, if there is a 50 percent probability that it will rain, and rain will result in a $100 loss, the expected monetary value of the rain event is $50 (.5 x $100).
Compressing the project schedule by overlapping activities that would normally be done in sequence, such as design and construction. Sometimes confused with concurrent engineering.
A network diagramming technique in which events are represented by boxes (or nodes) connected by arrows to show the sequence in which the events are to occur. Used in the original Program Evaluation and Review Technique.
Document that includes only major variations from plan (rather than all variations).
The expected total cost of an activity, a group of activities, or of the project when the defined scope of work has been completed. Most techniques for forecasting EAC include some adjustment of the original cost estimate based on project performance to date. Also shown as “estimated at completion.” Often shown as EAC = Actuals-to-date + ETC.
The expected additional cost needed to complete an activity, a group of activities, or the project. Most techniques for forecasting ETC include some adjustment to the original estimate based on project performance to date.
The number of labor units
An assessment of the likely quantitative result. Usually applied to project costs and durations and should always include some indication of accuracy (e.g., ± x percent). Usually used with a modifier (e.g., preliminary, conceptual, feasibility). Some application areas have specific modifiers that imply particular accuracy ranges (e.g., order-of-magnitude estimate, budget estimate, and definitive estimate in engineering and construction projects).
required toother complete an activity or project element. Usually expressed as staffhours, staffdays, or staffweeks. Should not be confused with duration. In the critical path method, the earliest possible point in time on which the uncompleted portions of an activity (or the project) canand start, based on the network logic any schedule constraints. Early start dates can change as the project progresses and changes are made to the project plan.
(1) A method for measuring project performance. It compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance is as planned. See also actual cost of work performed, budgeted cost of work scheduled, budgeted cost of work performed, cost variance, cost performance index, schedule variance, and schedule performance index. (2) The budgeted cost of work performed for an activity or group of activities.
Early Finish Date (EF)
Duration Compression
Duration
Dummy Activity
D e liv er a ble
Data Date
Current Start Date
Current Finish Date
Critical (CPM) Path Method
Critical Path
Shortening the project schedule without reducing the project scope. Duration compression is not always possible and often requires an increase in project cost.
In the critical path method, the earliest possible point in time on which the uncompleted portions of an activity (or the project) can finish based on the network logic and any schedule constraints. Early finish dates can change as the project progresses and changes are made to the project plan.
An activity of zero duration used to show a logical relationship in the arrow diagramming method. Dummy activities are used when logical relationships cannot be completely or correctly described with regular activity arrows. Dummies are shown graphically as a dashed line headed by an arrow.
The number of work periods (not including holidays or other non-working periods) required to complete an activity or other project element. Usually expressed as workdays or workweeks. Sometimes incorrectly equated with elapsed time.
The point in time that separates actual (historical) data from future (scheduled) data. Also called as-of date.
Any measurable, tangible, verifiable outcome, result, or item that must be produced to complete a project or part of a project. Often used more narrowly in reference to an external deliverable, which is a deliverable that is subject to approval by the project sponsor or customer.
The current of the pointestimate in time when an activity will be completed.
The current of the pointestimate in time when an activity will begin.
In a project network diagram, the series of activities which determines the earliest completion of the project. The critical path will generally change from time to time as activities are completed ahead of or behind schedule. Although normally calculated for the entire project, the critical path can also be determined for a milestone or subproject. The critical path is usually defined as those activities with float less than or equal to a specified value, often zero.
A network analysis technique used to predict project duration by analyzing which sequence of activities (which path) has the least amount of scheduling flexibility flexibility (the least amount of float). Early dates are calculated by means of a forward pass using a specified start date. Late dates are calculated by means of a backward pass starting from a specified completion date (usually the forward pass’s calculated
project early finish date).
C r it ic a l A c t i vi t y
Crashing
Cost Variance (CV)
Cost Plus Incentive Fee (CPIF) Contract
Cost Plus Fixed Fee (CPFF) Contract
Cost Performance Index (CPI)
Cost of Quality
Cost Estimating
Cost Control
Cost Budgeting
Taking action to decrease the total project duration after analyzing a number of alternatives to determine how to get the maximum duration compression for the least cost.
Any activity on a critical path. Most commonly determined by using the critical path method. Although some activities are “critical” in the dictionary sense without being on the critical path, this meaning is seldom used in the project context.
A type of contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.
(1) Any difference between the estimated cost of an activity and the actual cost of that activity. (2) In earned value, BCWP less ACWP.
The ratio of (BCWP/ACWP). budgeted costsCPI to actual costs is often used to predict the magnitude of a possible cost overrun using the following formula: original cost estimate/CPI = projected cost at completion.
A type of contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).
The costs incurred to
Estimating the cost of the resources needed to complete project activities. Allocating the cost estimates to individual project components.
ensure quality. The cost of quality includes quality planning, quality control, quality assurance, and rework.
Controlling changes to the project budget.
Corrective Action
Control Charts
Control
Contract Close-out
Contract
What are the 3 general types of contracts?
Fixed price or lump sum contracts
Cost reimbursable contracts
Unit price contracts
Contingency Reserve
Control charts are a graphic display of the results, over time and against established control limits, of a process. They are used to determine if the process is “in control” or in need of adjustment.
Changes made to bring expected future performance of the project into line with the plan.
Completion and settlement of the contract, including resolution of all outstanding items.
The process of comparing actual performance with planned performance, analyzing variances, evaluating possible alternatives, and taking appropriate corrective action as needed.
Fixed price or lump sum contracts, Cost reimbursable contracts, Unit price contracts
A contract is a mutually binding agreement which obligates the seller to provide the specified product and obligates the buyer to pay for it.
This type of contract involves payment (reimbursement) to the contractor for its actual costs. cost s. Costs are usually classified as direct costs (costs
This type of contract involves a
incurred directly by the project, such as wages for members of the project team) and indirect costs (costs allocated to the project by the performing organization as a cost of doing business, such as salaries for corporate executives). Indirect costs are usually calculated as a percentage of direct costs. Cost reimbursable contracts often include incentives for meeting or exceeding selected project objectives such as schedule targets or total cost.
A separately planned quantity used to allow for future which may besituations planned for only in part (sometimes called
fixed total Fixed price for a well-defined product. price contracts may also include incentives for meeting or exceeding selected project objectives such as schedule targets.
With this type of contract the contractor is paid a preset amount per unit of service (e.g., $70 per hour for professional services or $1.08 cubic yard of earth removed) andper the total value of the contract is a function of the quantities needed to complete the work.
known unknowns ).
Do you include contingency reservers in the schedule baseline?
Why would you use contingency reserves?
Are contingency reservers only used when dealing with costs?
Contingency Planning
Concurrent Engineering
Communications Planning
Code of Accounts
Chart of Accounts
Change Board Control (CCB)
Calendar Unit
Contingency reserves are intended to reduce the impact of missing cost or schedule objectives.
Yes, contingency contingen cy reserves are normally included in the project’s cost and schedule baselines.
The development of a management plan that identifies alternative strategies to be used to ensure project success if specified risk events occur.
No, contingency reserves may involve cost, schedule, or both.
Determining the information and communications needs of the project stakeholders.
An approach to project staffing that, in its most general form, calls for implementors to be involved in the design phase. Sometimes confused with fast tracking.
Any numbering system used to monitor project costs by category (e.g., labor, supplies, materials). The project chart of accounts is usually based upon the corporate chart of accounts of the primary performing organization.
Any numbering system used to uniquely identify each element of the work breakdown structure.
The smallest unit of time used in scheduling the project. Calendar units are generally in hours, days, or weeks, but can also be in shifts or even in minutes. Used primarily in relation to project management software.
A formally constituted group of stakeholders responsible for approving or rejecting changes to the project
baselines.
Budgeted Cost of Work Scheduled (BCWS)
Budgeted Cost of Work Performed (BCWP)
Budget At Completion (BAC)
Baseline
Bar Chart
Gantt chart
Backward Pass
Arrow Diagramming Method (ADM)
Arrow
Application Area
The sum of the approved cost estimates (including any overhead allocation) for activities (or portions of activities) completed during a given period (usually project-to-date).
The sum of the approved cost estimates (including any overhead allocation) for activities (or portions of activities) scheduled to be performed during a given period (usually project-to-date).
The original plan (for a project, a work package, or an activity), plus or minus approved changes. Usually used with a modifier (e.g., cost baseline, schedule baseline, performance measurement baseline).
The estimated total cost of the project when done.
A graphic display of schedule-related information. In the typical bar chart, activities or other project elements are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars. Also called a Bar chart.
A graphic display of schedule-related information. In the typical bar chart, activities or other project elements are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal bars. Also called a Gantt chart.
A diagramming technique in which activities are represented by arrows.
The calculation of late finish dates and
The tail of the arrow represents the start and the head represents the finish of the activity. Activities are connected at points called nodes to illustrate the sequence in which the activities are expected to be performed.
late start dates the uncompleted portions of allfor network activities. Determined by working backwards through the network logic from the project’s end date. The end date may be calculated in a forward pass or set by the customer or sponsor.
A category of projects that have common elements not present in all projects. Application areas are usually defined in terms of either the product of the project or the
The graphic presentation of an activity.
type of customer.
Is stakeholder managerment a proactive task?
What is the triple constraint and what is it used for?
What is meant by the word internationalization?
What is Social-Econominc Environmental Sustainability?
Should you incorporate stakeholders' requirements into a project?
What does the initiating process do? do ?
What is the meant by the planning process?
What is down in the executing process?
What is done in the controlling process?
What is done in the closing process?
The triple constraint is time, cost, quality. It is used to identify the three most important factors that a project manager needs to consider in a project.
Yes, stakeholder management is a proactive task.
Being accountable for impacts resulting from a project both social and economic.
Consideration of time-zone differences, national and regional holidays. travel requirements, and other logistical issues.
It authorizes the project of phase.
Yes, always always incorporate the stakeholder's requirements into the project.
During this phase people are coordinating with other resources to carry out the project phase or plan.
This process is used for defining and refining objectives and selecting the best of the alternatives.
This process is when formailizing acceptance
This process is for ensuring that project objectives are met by monitoring and measuring progress in order to indetify variances from the plan so that corrective action can be
ofisthe project orinphase completed the hopes of bringing it to
an orderly end.
taken if and when necessary.
What is a tight matrix?
In a strong matrix what type of power/authority does the project manager have?
In a weak matrix does the project manager have much authority?
Project Coordinator
Project Expeditor
What are some advantages/benefits of a functional organization?
What are some disadvantages of a functional organization?
Isnecessary scope verification when a project is terminated?
Will manageme management nt byifobjectives work management doesn't support it.
Dephi Technique
In this type of matrix the power rests with the project manager.
This refers to locating the offices for the project team in the same room/location.
An individual who reports to a higher-level manager in the organization, has the authority to assign work to individuals in various functional organizations, and shares authoity and resources with the functional manager.
No, the power/authority rests with the functional manager.
1) Easier management o specialist's, 2) Team memebers only report to 1 boss, 3) Clearly defined careeer paths, 4) resources are centralized.
An individual who is a staff assistant to an executive who has the ultimate responsibility for the project. Has authority only in his managers department but not over resources from other departments departments..
Yes, scope verifcation verif cation is
1) The project manager
necessary when a project is terminated, it althoughs the organization to determine the level of completion.
has NO authority, 2) People place more emphasis on their speciality than to the project.
A mthod to obtain opinions on issues. Information sent to experts, responses are compiled and the results are sent back for further review. Using the delphi technique helps reduce bias and undue influence.
No, in orer to work properly, it must supported by be management.
What type of diagram uses dummy activities?
What are the three uses for dummy activites?
What is the expectancy theory?
What is problem solving/confrontation?
Give three examples of hygiene factors in Herzberg's theory of motivation. How do they affect motivation.
What is McGregor's Theory X?
What is McGregor's theory Y?
What is the purpose of a resource Gantt chart?
What is an organizational breakdown structure (OBS)? Does the matrix form of project organization facilitate or complicate project
team development?
1) logic, 2) time delay and, 3) uniqueness.
Activity-On-Arrow Network.
Addressing conflict directly by getting the parties to work together to define the problem, collect information, develop and analyze alternatives, and select the most appropriate alternative.
It holds that people tend to be highly productive and motivated if they believe their efforts will lead to successful results and they will be rewarded for their success.
Traditional approach: workers y motivation, are self-centered, lazy, lacking ambition. Managers organize the elements of the productive enterprise in the interest of economic ends.
Pay, attitude of supervisor, and working conditions. but improving hygiene factors in not likely to increase motivation. Motivators are an opportunity to achieve and experience self-actualization.
A specific type of organizational chart that shows which units are responsible for which work items
resistant to organizational needs; they are willing and eager to accept responsibilities and are concerned with self-growth self-growth and fulfillment.
It complicates team development because
It identifies when a
team members are a accountable to both functional manager and
particular is or will beresource working on a particular task.
Workers are not by nature
a project manager.
Name three major forms of project organizational structure.
What is a projectized organization?
Describe the difference between a weak matrix and a strong matrix.
What is a project "war room" and what is its benefit?
What is variance analysis?
What is active listening?
What of is conflict major cause with functional managers?
What is most difficult conflict to deal with?
What is earned value analysis and how is it used in performance
What is the tool for used for communication planning?
reporting?
One in which a separate, functional organization is established for each project. Personnel are assigned on a full-time basis.
Functional, Matrix, and Projectized
A single location for the team to get together for any purpose. It provides a repository for project artifacts, records, and up-to-date schedules and status reports. It gives an identity to the project team.
Weak matrices are similar to functional organizations. Strong matrices are similar to projectized organizations (with balance of power tipped toward the project manager)
Listening in which the recipient is attentive and asks for clarification of ambiguous messages
Comparing actual project results to planned or expected results in terms of cost, schedule, scope, quality, and risk.
Personality conflicts
Schedules
An analysis that integrates cost and
Stakeholder analysis
schedule measures. It is used to help the project management team assess
The FROM activity must START before the TO activity can FINISH.
The FROM activity must FINISH before the TO activity can FINISH.
Cannot be in CPM or PERT. Can be in GERT
The FROM activity must START before the TO activity can FINSH.
Summary-level schedule that identifies key milestones.
Cost and schedule buffers planned by management for unseen events that would impact the project.
Significant event.
Project and Functional managers share
responsibilities.
Mitigation
Modern Project Management
Monitoring
Monte Carlo Analysis
Near-Critical Activity
Network Analysis
Network Logic
Network Path
Node
Organizational Breakdown Structure
Broad / Not focused on cost and time / Focused on: scope, cost, time quality, risk, etc.
Steps to lessen risk by lowering probability.
Simulation of Risk that occurs throughout the project.
Tracking and reporting project performance and status.
The process of identifying early and late finish dates for the uncompleted portions of project activities.
An activity that has low total float.
Connected activities in the project network diagram.
A collection of dependencies that make up the project network diagram.
A depiction of the project into work breakdown
A junction point in a project network diagram.
packages .
Organizational Planning
Overall Change Control
Parametric Estimating
Pareto Diagram
Path
Path Convergence
Percent Complete
Performance Reporting
Performing Organization
Precedence Diagramming Method
Coordinating changes across the entire project.
Identifying, documenting and assigning project roles, responsibilities and reporting relationships.
Histogram ordered by frequency of occurrence that shows multiple results relating to one cause.
Estimates based on statistics and history.
Parallel paths that lead to one milestone, but may singularly delay a project.
Sequential activities.
Collecting and disseminating information about project performance to help ensure project progress.
Percent of work already performed.
Activities represented byare boxes and linked sequentially.
The enterprise employees arewhose most directly involved in doing
A diagramming method.
the work of the project.
Precedence Relationship
Predecessor Activity
Procurement Planning
Program
Program Evaluation and Review Technique
Project
Project Charter
Project Communications Management
Project Cost Management
Project Human Resource Management
1 - Arrow Diagramming Method - Activity which enters a NODE. / 2 Precedence Diagramming Method - Activity which goes "away from" the NODE.
Refers to the diagramming methods.
A group of related projects. Usually on-going.
Determining what to procure and when.
A temporary endeavor undertaken to create a unique product or service.
Event-oriented. Used to estimate project duration. Used for projects with uncertainly in duration.
Subset project for collecting and dispersing project info.
Sr. Management's written authority given to the PM for organization resources.
Subset project for effectively using
Subset project for ensuring a project is
personnel in the project.
completed within budget.
Project Integration Management
Project Life Cycle
Project Management
Project Management Body of Knowledge
Project Management Software
Project Management Professional
Project Management Team
Project Manager
Project Network Diagram
Project Phase
A collection of sequential project phases.
Subset project for integrating subset projects into the whole.
Book of proven project management practices.
The knowledge, skills, tools and techniques to meet and exceed a stakeholders expectations with a project.
Certified PM from PMI
Computer application designed to plan and control a project.
Individual responsible for managing the project.
Members of the project team.
A subset collection of project activities.
PERT or GANTT Schematic display of
project activities.
Project Plan
Project Plan - Elements
Is a Project Plan Summary or Detailed?
Project Plan Development
Project Plan Execution
Project Planning
Project Procurement Management
Project Quality Management
Project Risk Management
Project Schedule
Plan / Cost Assumptions / Schedule / Decisions / Scope
Formal document used to guide the project.
Taking the results of other planning processes and putting them into a new document.
Can be both
Development and maintenance of the project plan.
Carrying out the project plan details.
Subset of the project used to ensure the project is up to requirements at delivery.
Acquiring goods and services outside of the project team for use in the project.
Outlines dates for each activity in sequential
Subset of the project for identifying and mitigating
order.
risks.
Project Scope Management
Project Team Members
Project Time Management
Projectized Organization
Quality Assurance
Quality Control
Quality Planning
Remaining Duration
Request for Proposal
Request for Quotation
They work for the Project Manager
Subset of the project used to ensure only the pre-defined work required is done and no more.
Where PM has 100% over project team. No shared authority.
Subset of the project that monitors and ensures a team meeting all milestone dates.
Process of evaluating specific project steps to verify they meet with the project quality standards.
Evaluating process to ensure the project will satisfy its quality standards.
Time needed to complete an activity.
Identifying which quality standards are relevant to the project.
Bid document from a company to a vendor for
Bid document from company to vendor.
pricing information.
Reserve
Resource-Limited Schedule
Responsibility Assignment Matrix
Resource Leveling
Resource Planning
Retainage
Risk Event
Risk Identification
Risk Quantification
Risk Response Control
Where scheduling concerns are addressed by resource management concerns.
Provision in the project plan to mitigate cost and/or schedule risks.
Resource identification process.
Project where start and end date are based on resource availability.
Down payment on a contracted product or service.
Relates project organization structure to work breakdown structure.
Identifying which risks will affect the project.
An occurrence that affects the projects outcome.
Responding to changes in risk over the course of
Identifying probability of
the project.
the risk.
Risk Response Development
S-Curve
Schedule Control
Schedule Development
Schedule Performance Index
Schedule Variance
Scheduled Finished Date
Scheduled Start Date
Scope
Scope Change
Graph showing cumulative cost and labor over time.
Risk mitigation plan
Analyzing activity sequences, durations and resource requirements to create a project schedule.
Controlling changes to the project schedule
Difference between scheduled and actual timeframes.
Work performed / Work Schedule (BCWP / BCWS)
Planned activity start date
Planned activity end date
Any change to the scope.
The sum of the products and services to be
provided as a project.
Scope Change Control
Scope Definition
Scope Planning
Scope Verification
Should-Cost Estimate
Slack
Solicitation
Solicitation Planning
Source Selection
Staff Acquisition
Decomposing the major deliverables into small parts.
Controlling changes in the scope.
Auditing each scope element at the end of a project for completion.
Written scope statements.
Used in PERT for FLOAT
Used to judge the reasonableness of a vendors quote.
Document stating requirements and potential sources to meet those requirements.
Obtaining quotes, bids and offers.
Getting human resources
Choosing a vendor or
to work on the project.
product.
Stakeholder
Start Date
Statement of Work
Subnet
Successor Activity
Target Completion Date
Team Development
Time-Scaled Network Diagram
Target Finish Date
Target Start Date
Qualified starting date
People directly or indirectly involved in the project.
Subproject
A narrative description of products or services to be supplied under contract.
A constraining date in the project diagram.
Activity while "leaves" the node.
Diagram where the physical shape of each activity object is proportional to the duration of that activity.
Developing team members to enhance the project.
The date the work for the activity is planned to be
The date the work for the activity is planned to be
started by.
completed by.
How is contract closeout similar to administrative closeout?
How is performance reporting used as a tool for contract administration?
When are payment requests an output of contract administration?
Describe the characteristics of a unilateral contract?
What is a unilateral contract?
Under what two conditions must PMI members refrain from offering or accepting monetary payments or other forms of compensation or tangible benefits?
What is the most critical culture for the success of a project manager working internationally?
Who can initiate an ethics complaint?
When is a PMP
What are the two
responsible for reporting to PMI possible
conditions under which PMI member's do not have
violations of the PMP Code of Professional Conduct?
to honor and maintain the privacy and confidentiality of client information?
it provides management with information about how effectively the seller is achieving the contractual objectives.
Both contract closeout and administrative closure involve product verification. However, the contract terms and conditions may prescribe specific procedures for contract closeout.
It usually takes the form of a purchase order -- a standard form listing routine items at standard prices.
When the project is using an external payment system.
When payments do not conform with applicable laws and when they may provide an unfair advantage for themselves or their business.
A contract that has only one signature (the issuer).
Any person, group, or organization, including PMI.
Leadership
1) if granted permission by theemployer, customer, client, and 2) If or
When reasonable and clear facts exist to verify
maintaining the confidentiality is otherwise unethical or unlawful.
the violation.
What is the best way to demonstrate a professional and cooperative manner with team members or other stakeholders?
What is the purpose of the procurement management plan?
What are two outputs from contract closeout?
What is a procurement audit? How is it used?
During which process are the impact and likelihood of identified risks assessed so that they may be prioritized according to their potential effect on project objectives?
How is expected monetary value computed?
What is a SWOT analysis and how is it used?
What action should the project manager take to ensure that each risk response plan is implemented and monitored?
What type of contract documentation should be
What are five success factors for doing
reviewed in contract closeout?
business internationally?
To describe how solicitation planning, solicitation, source selection, contract administration, and contract closeout will be managed.
By respecting cultural, ethnic and personal differences.
A comprehensive analysis and review of the process from procurement planning through contract administration. It is used to identify successes and failures, which can be applied as lessons learned to other projects.
The contract file, and formal acceptance and closure.
Expected monetary value is the product of two numbers: risk event probability (probability risk will occur) and risk event value (estimate if it does happen, the loss that will be incurred).
Qualitative risk analysis
Identify to and assign individual own eachan risk who will take personal responsibility for protecting the project objectives from the risk's impact.
A strengths, weakness, opportunities, and threats analysis. Used in risk identification, it tends to increase the number of project risks considered.
1) Cultural
The contract itself and all associated schedules, requested
understanding, 2) Cross-cultural journeys,
and approved contract changes, seller developed technical
3) Good communication, 4) Negotiation, and 5) Global management
documentation, seller performance reports, financial documents, and contract-related inspection reports
What is the difference between attribute sampling and variable sampling?
In which project phase is quality control performed?
What is the difference between a tolerance and a control limit?
What are the three (3) key outputs from administrative closure?
Name five barriers to effective project communications.
Name three communications channels in an organization?
Why is communications planning so tightly linked to project organizational planning?
What is active listening?
What is earned value analysis and how is it
List the four parts of the
used in performance reporting?
communication model.
Quality control is performed throughout all phases of the project life cycle.
Attribute sampling determines whether the result does or does not conform to the specifications. In variable sampling, the result is rated on a continuous scale that measures the degree of conformance within a pre-established acceptable range.
A tolerance establishes the range of acceptable results. A control limit is computed based on the results themselves.
Personal, Organization, Grapevine
1) Lack of clear communication channels. 2) Physical distance between communicator and receiver, 3) Difficulties with technical language, 4) Distracting environmental factors, 5) Detrimental attitudes.
Listening in which the recipient is attentive and asks for clarification of ambiguous messages.
Because the project's organizational structure will have a major effect on project communications. An analysis that integrates
Communicator, Message,
cost and schedule measures. It is used t help
Medium, Recipient
the project management team assess project performance.
What is the difference between a risk and a problem?
When should EAC be calculated by AC + BAC EV?
When should EAC be calculated by AC + (BAC - EV) / CPI?
What does the benefit-cost ratio not tell you?
if a project is experiencing quality problems, should the project manager devote more resources to inspection of to prevention?
What are the seven (7) main quality control tools, often called the "basic seven" tools?
does the matrix form of project organization facilitate or complicate project team development? Why?
Project Human Resource Management comprises which three processes?
How is simulation used in activity duration estimating and what is
At which phase(s) in the project life cycle is significant risk thought
the most common type of simulation?
to have the greatest impact?
When current variances are seen as atypical, and the project management team's expectation is that similar variances will not occur in the future.
A risk is a future event; it has not yet occurred. A problem, on the other hand, currently exists.
The absolute value of the benefit or cost.
When the current variances are seen as typical of future variances.
General management skills, product skills & knowledge, work authorization system, project management information system (PMIS), and organization procedures
Product description, strategic plan, project selection criteria, and historical information
Change control system, configuration management, performance measurements, additional planning, and project management information system (PMIS)
Product analysis, benefit/cost analysis. alternative identification and expert judgement
Project selection methods, expert judg ju dgem ement ent
Product description, WBS templates and decomposition
project charter, constraints, and
assumptions
Scope Definition Inputs
Scope Verification Tools
Scope Verification Input
Scope Change Control - Tools
Scope Change Control - Inputs
Activity Definition Tools
Activity Definition Inputs
Activity Sequencing Inputs
Activity Sequencing Tools
Project Plan Development - Input
Inspection
Scope statement, constraints, assumptions, other planning outputs, and historical information
Scope change control system, performance measurement,, and measurement additional planning
Work results, product documentation, WBS, scope statement and project plan
Decomposition and Decomposition templates
WBS, performance reports, change requests, and scope management plan
Communicatio Communication n skills, information retrieval systems, and information distribution systems
Communications requirements, communications technology, constraints, and assumptions
Performance reviews, variance analysis, trend analysis, earned value
Work results,
communications
analysis, and information distribution tools
management plan, and project plan
Administrative Closure - Inputs
Administrative Closure - Tools
Performance Reporting - Inputs
Risk Management Planning - Inputs
Risk Management Planning - Tools
Risk Identification Tools
Risk Identification Inputs
Qualitative Risk Analysis - Tools
Qualitative Risk
Organizational
Analysis Input
Planning Tools
Performance reporting tools, project reports, and project presentations
Performance measurement documents, product documentation, and other project records
Project charter, organizational risk management policies, defined roles and responsibilities, stakeholder risk tolerance, organization's risk management templates, and the WBS
Project plan, work results, and other project records
Documentation review, information gathering techniques, checklists, assumptions analysis, and diagramming techniques
Planning Meetings
Risk probability and impact, probability/impact risk rating matrix, project assumptions testing, and data precision ranking
Riskproject management plan, planning outputs, risk categories, and historical information
Templates, human
Risk management plan, identified risks, project status, project type, data
resource practices, organizational theory,
and stakeholder analysis
precision, scales of probability and impact, and assumptions
Risk Monitoring & Control Tools
Quantitative Risk Analysis - Inputs
Procurement Planning - Tools
Risk Monitoring and Control - Inputs
Solicitation - Tools
Solicitation Planning Inputs
Solicitation Planning Tools
Procurement Planning - Inputs
Solicitation - Inputs
Source Selection -
Inputs
Risk management plan, identified risks, list of prioritized risks, list of risks for additional analysis, historical information, expert judgment, and other planning outputs
Project risk response audits, periodic project risk reviews, earned value analysis, technical performance measurements, and additional risk response planning
Risk management plan, risk response plan, project communication, additional risk identification and analysis, and scope changes
Make of buy analysis, expert judgment, and contract type selection
Procurement management plan, statement of work, and other planning outputs
Bidders conferences, and advertising
Procurement Planning - Inputs
Standard forms and expert judgment
Proposals, evaluation criteria, and
Procurement documents, and
organizational policies
qualified seller lists
Source Selection Tools
Quality Control Outputs
Contract Close-out Inputs
Contract Close-out Tools
Contract Administration - Inputs
Contract Administration - Tools
Project Plan Execution - Outputs
Organizational Planning - Outputs
Project Plan
Quantitative Risk
Development - Outputs
Analysis - Tools
Quality improvement, improvement, acceptance decisions, rework, completed checklists, and process adjustments
Contract negotiation, weighting system, screening system, and independent estimates
Procurement Audits
Contract Documentation
Contract change control systems, performance reporting, and payment systems
Contract, work results, change requests, and seller invoices
Role and responsibility assignments, staffing management plan, oganization charts, and supporting details
Work results, and change requests
Interviewing, sensitivity analysis,
Project plan, and
decision tree analysis, and simulation
supporting details
Schedule Development - Outputs
Quantitative Risk Analysis - Outputs
Activity Duration Estimating - Outputs
Qualitative Risk Analysis - Outputs
Activity Sequencing Outputs
Risk Identification Outputs
Activity Definition Outputs
Risk Management Planning - Output
Scope Change Control
Administrative Closure
- Outputs
- Outputs
Prioritized list of quantified risks, probabilistic analysis of the project, probability of achieving the cost and time objectives, and trends in quantitative risk analysis results
Overall risk ranking for the project, list of prioritized risk, list of risks for additional analysis and management, trends in qualitative risk analysis results
Activity duration estimates, basis of estimates, and activity list updates
Risks, triggers, and inputs to other processes
Project network diagrams, and activity list updates
Risk Management Plan
Activity list, supporting details, and work breakdown structure updates
Project project archives, closure,
Scope changes, corrective action,
lessons learned
lessons learned, and adjusted baselines
Scope Verification Outputs
Performance Reporting - Outputs
Scope Definition Outputs
Information Distribution - Outputs
Scope Planning Output
Communication Planning - Output
Initiation - Outputs
Team Development Output
Integrated Change
Staff Acquisition -
Control - Output
Outputs
Performance reports, and change requests
Formal Acceptance
Project records, project reports, and project presentations
Work breakdown structure, and scope statement updates
Communications management plan
Scope statement, supporting details, scope management plan
Performance improvements, and inputs to performance appraisals
Project charter, project manager identified and assigned, constraints, and assumptions
Project staff assigned, and project team
Project plan updates, corrective action, and
directory
lessons learned
Resource Planning Output
Risk Monitoring and Control - Outputs
Schedule Control Outputs
Risk Response Planning - Outputs
Schedule Development - Outputs
Risk Response Planning - Outputs
Risk Response Planning - Inputs
Risk Response Planning - Tools
Contract Close-out -
Contract Administration -
Outputs
Output
Workaround plans, corrective action, project change requests, updates to risk response plan, risk database, and updates to risk identification checklists
Resource requirements
Risk response plan, residual risks, secondary risks, contractual agreements, contingency reserve amount needed, inputs to other processes, and inputs to a revised project plan
Schedule updates, corrective action, and lessons learned
Risk response plan, residual risks, secondary risks, contractual agreements, contingency reserve amounts needed, Inputs to other processes, and inputs to a revised project plan
Avoidance, transference, mitigation, and acceptance
Risk management plan, list of prioritized risks, risk ranking of the project, prioritized list of quantified risks, probabilistic analysis of the project, list of potential responses, risk thresholds, risk owners, common risk causes, trends in quality and quantitative analysis results
Correspondence, contract changes, and
Contract file, andand formal acceptance
payment requests
closure
Quality Planning Output
Source Selection Output
C os t C o n t ro l - O u t p ut s
S ol i c i t at i o n - O ut p u t
Cost Budgeting Outputs
Solicitation Planning Outputs
Cost Estimating Outputs
Procurement Planning - Outputs
Quantitative Risk
Analysis - Outputs
Contract
Quality management plan, operational definitions, checklists, and inputs to other processes
Proposals
Revised cost estimates, budget updates, corrective action, estimate at completion, project closeout, and lessons learned
Procurement documents, evaluation criteria, and statement of work updates
Cost baseline
Procurement management plan, and statements of work
Cost estimates, supporting detail, and cost management plan
Prioritized list of quantified risks, Probabilistic analysis of the project, Probability of
achieving the cost & time objectives, trends in quantitative risk
Total Float
Total Quality Management
Workaround
Work Breakdown Structure
Work Item
Work Breakdown Structure
Quality improvement program.
Float
Deliverable oriented approach. / Project elements are rolled up into larger project deliverables.
An alternative risk mitigation plan. Leaves Risk in place.
Lowest level deliverable. / May be divided into activities.