Fast Fast Tracking projects

Published on September 2020 | Categories: Documents | Downloads: 11 | Comments: 0 | Views: 118
of 3
Download PDF   Embed   Report

Comments

Content

 

FastTracking: Fasttrackingisamanagementtechniqueusedtoensurethatprojectsarecomplet edwithintheshortesttimepossible.Whenprojectsarefast-tracked,itusually indicatesthattaskshavebeenarrangedtotakeadvantageofnon-dependentacti vitiesthatcanoccursimultaneously,thusshorteningtheoverallprojecttimeli ne.But,thereismoretofast-trackingthanthesequencingoftasksandactivit ies.  Isfast-trackingappropriateforyouandyourcurrentproject? Beforeyoucansafelyfast-trackaproject,youmustfirstaddressafewassumpt ions... Youmusthavearealisticschedule,withalltasksandactivitiesproperlyident ified. Youmustbeawareofalltaskdependencies(knowingwhichtasksmustendbefore otherscanbegin). Youmusthaveasolidgrasponprojectrequirements,objectivesandpriorities. Youmusthaveagoodrelationshipwithyourend-usersandmanagement. Youmusthaveagoodprocessfortrackingprogressandmanagingrisksandproble ms. Onceyoucanmeetalltheseassumptions,youwillthenhavetoaddressyourneed s....whydoyouneedtofast-tracktheproject? Fast-trackingcanbeappropriateunderanumberofcircumstancesandconditions. Itisimportanttonotethatfast-trackinghasitsrisks...mostnotably;ap rojectthatisonthefasttrackcanbehardertomanagebecauseofallthesimu ltaneousactivity.Inaddition,ifandwhenproblemsoccur,thenegativeimpact canbemoreseriousconsideringtheextentofactivityunderway.So,fast-trac kingshouldbecarefullyconsidered.  Whenisfast-trackingappropriate? Theprojecthastobecompletedwithintheshortesttimepossibletomeetrequir edbusinessneedsandobjectives. Theprojecthastobecompletedsoonerthanexpectedduetochangingcircumstanc es. Theprojectisbehindscheduleandtheremainingtaskshavetobestreamlinedto makeupforlosttime. Theprojectisintrouble,andfast-trackingisneededtominimizefurtherlosse sanddamage. Whenfacedwiththeneedtofast-trackaproject,thefirstthoughtmaybetoad dresources,orevenmorelikely,toputinmoreworkhours.Buttheseoptions arenotalwaysproductiveorviable. Theapplicationofadditionalstaffresources,whichmaynotevenbeapossibili ty,isoftennotasolution.Undersomeprojectcircumstances,nomatterhowma nyresourcesyouadd,certaintaskscanonlybecompletedbyafinitenumberof resources.Additionalresourcesmayonlycauseconfusion,andinfact,mayimpe de,ratherthatpromoteprogress. Overtimeisalsoatrickyproposition.Whileadditionalworkhoursmayshorten anotherwiselaggingschedule,excessiveovertimemaybackfireifstaffburn-out setsin.

 

Consideringtheseissues,fast-trackingmaybebestusedasastrategicweapon, whereyoufirstlooktotheprojectscheduleandthentheprojectitselftoensu rethatallefficienciesarebeingmet. TheFast-TrackProcess StepOne:UnderstandyourGoals&Capabilities Whydoyouneedtofast-track? Areyoulookingforprojectefficienciesortosolveproblems? Doyouhavetheskillsandresourcesneededtoproperlymanagethisprojectonce itisonthefast-track.  StepTwo:ExaminetheProjectSchedule Identifyharddependencies(thosetaskswhichhavea"finish-start"relationsh ipthatcannotbechanged). Identifysoftdependencies(thosetaskswhichcanpossiblybemodifiedtoremove dependencies) Identifyconcurrenttasks(taskshavingnodependenciesandcanoccursimultaneo usly).Thisisthekeytofasttracking.  StepThree:Re-worktheProjectTimeline Havingidentifiedconcurrenttasks,createaschedulethatallowsthesetasksto becompletedintheshortesttimepossible. Breakdownsoftdependenciesintotasksub-sets,removingdependenciestoshorte ntheprojecttimeline. Focusontheremainingharddependencies,assigningrotatingstaff,workingins hifts,toallowmoretimetobespentoneachtask,thusshorteningtheoverall timeline. StepFour:ExamineAlternatives Canadditionalresourcesbeadded,andtowhichprojecttaskscanthoseresource sbestbeapplied? Canadditionalworkhours(overtime)beauthorized,andhowshouldthoseadditio nalhoursbeapplied? Canthescopeoftheprojectbechangedtoshortentheprojectschedule? Candeliverablesfunctionalitybereducedtoshortentheprojectschedule? Cantheprojectbeoutsourcedinordertoshortentheprojectschedule?  StepFive:WeighAlternatives Asyouexamineandconsiderthesefast-trackalternatives,youneedtoweigheac halternativeagainst.... Time:Howmuchtimedoyouneedtosave? Gain:Whatbenefitswillberealizedfromfast-tracking? Costs:Whatcostswillbeincurredfromfast-tracking? Impact:Whatwilltheimpactbeonstaff,andonotherprojectsalreadyunderwa y?   Step6:SeekConsensus

 

Beforeyoufast-trackaproject,youshouldensurethatyouranalysisiscomplet e,andthatyouhavethebuy-inofthosewhowouldbeimpactedbythefast-track decision,includingstaffandend-users.Youmayneedtofast-trackwithoutto talagreement,butcooperationwillbegreatlyenhancedifallpointsofviewar econsidered.  Step7:MonitorProgressandTrackProblems Onceinfast-trackmode,effectiveissuestrackingandproblemmanagementbecome sessential.Bydefinition,afast-trackprojectwillbeproceedingatanaggre ssivepace,andtherewillbesignificantactivitygoingonatonce.Theluxury offinishingonetaskandthenmovingonthenextwillbegone,sotheability totrackmultipletasksandmanageissuesandproblemswillbecriticaltosucce ss. ConcludedNote: Inalllikelihood,everyprojectcustomerwantstheirprojectcompletedasquick lyaspossible.Inandofitself,thisisnotareasontofast-track.Dependin guponthetypeofproject,theexperienceoftheprojectteamandtheresultsd esired,fast-trackingmaynotbeanoption.Sometimesaprojectmustproceedal ongatimelinethatcannotbeshortened,despitethebestintentions.However, whenusedwithdiscretionandefficiency,fast-trackingcanbeaproductivemean sforrespondingtochangingbusinessneedsandprojectcircumstances. GAUTAMKOPPALA POMEAuthor

Sponsor Documents

Or use your account on DocShare.tips

Hide

Forgot your password?

Or register your new account on DocShare.tips

Hide

Lost your password? Please enter your email address. You will receive a link to create a new password.

Back to log-in

Close